| System bathroom (dry) procedures | |||
|---|---|---|---|
| NO. | Construction | Procedure and works | |
| 1 | DBR | Install floor waterproof plate | |
| 2 | DBR | Install wall plate (include electricity & equipment water suppl | |
| 3 | DBR | Install ceiling plate | |
| 4 | Interior | PVC foam door frame installation work | |
| 5 | Plumbing | Install sewer, drain pipes | |
| 6 | Plumbing | water supply, drainage, piping, hydrostatic tests | |
| 7 | Plumbing | Bathroom masonry & curing (or lightweight partition) | |
| 8 | Others | Install fire damper | |
| 9 | Electrical | electricity panel construction | |
| 10 | Door | Install DOOR | |
| 11 | DBR | Install bathtub | |
| 12 | DBR | Install sink | |
| 13 | DBR | Install toilet | |
| 14 | DBR | Install faucet and accessories | |
| 15 | DBR | Install socket | |
| 16 | DBR | Install bathroom lamps | |
| 17 | Cleaning | Cleaning | |
| Total | 8 constructions | 17 procedures, 5 constructions, 1 electrical, 9 dry process |
|
| Conventional bathroom (wet) procedures | |||
|---|---|---|---|
| NO. | type | Construction | Procedure and works |
| 1 | Architecture | Internal | Install door frame |
| 2 | Electricity | Electricity | Electric wiring |
| 3 | Plumbing | Plumbing | Ceiling drain piping |
| 4 | Architecture | Masonry | Bathtub masonry & curing period |
| 5 | Architecture | Misc. | Install fire damper |
| 6 | Architecture | Misc. | Install marble SILL |
| 7 | Plumbing | Plumbing | Facility water supply piping |
| 8 | Plumbing | Plumbing | Water supply piping water pressure test |
| 9 | Electricity | Electricity | Electric wiring |
| 10 | Electricity | Misc. | cleaning & waste disposal directly/ door frame adjustment |
| 11 | Architecture | Waterproofing | Finishing works on waterproof boards & cleaning |
| 12 | Architecture | Waterproofing | Liquid waterproof 1 and curing |
| 13 | Architecture | Waterproofing | Liquid waterproof 2 and curing |
| 14 | Architecture | Waterproofing | Waterproofing with polyurethane on corner areas and curing |
| 15 | Architecture | Misc. | 2 cleaning & waste disposal directly/ door frame adjustment |
| 16 | Architecture | Misc. | Freshwater test (freshwater & drainage) |
| 17 | Architecture | Site management | Leak checks - staff |
| 18 | Architecture | Plasterwork | Rough inner wall plastering |
| 19 | Architecture | Plasterwork | Bathtub installation and curing |
| 20 | Architecture | Tile | Plasterwork wall/limited to once if patched |
| 21 | Architecture | Tile | Pressure-attach wall tile /calculate for additional procedure f |
| 22 | Plumbing | Plumbing | Drainage water pressure and acoustic insulation |
| 23 | Architecture | Interior | Bathroom ceiling installation (include access port) |
| 24 | Architecture | Marble | Floor mortar procedure and curing |
| 25 | Architecture | Marble | Floor mortar procedure and curing |
| 26 | Architecture | Marble | Installing joints to wall and floor tile |
| 27 | Architecture | Marble | Installing sink |
| 28 | Architecture | wallpaper | Wallpaper to bathroom ceiling |
| 29 | Architecture | Fixture | Install bathroom towel rack |
| 30 | Architecture | Glass | Install bathroom mirror |
| 31 | Plumbing | Plumbing | Installing toilet |
| 32 | Plumbing | Plumbing | Install faucet and accessories |
| 33 | Electricity | Electricity | Attach plugs |
| 34 | Lighting | Lighting | Install bathroom lamps |
| 35 | Architecture | Internal | Install DOOR |
| 36 | Architecture | Misc. | Install bathroom grille |
| 37 | Architecture | Corking | Corking works on corners, door frames, bathtub and sink area |
| 38 | Architecture | Misc. | 3 cleaning & waste disposal directly/ door frame adjustment |
| 39 | Architecture | Cleaning | Cleaning vendor works |
| Total | 17procedures | 39 procedures + additional direct misc. works Architecture : 23, Electricity : 4, Facility: 6, Dry method : 6 |
|
Conventional wet bathroom
| installation schedule (days) |
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 |
|---|---|---|---|---|---|---|---|---|---|---|---|
| Masonry wall construction | 2days | ||||||||||
| Floor and wall waterproofing work | 3days | ||||||||||
| Installation work of bath | 1day | ||||||||||
| Tile wall construction | 1day | ||||||||||
| Ceiling construction | 1day | ||||||||||
| Floor tiles construction | 1day | ||||||||||
| Sanitary equipment installation construction | 1day | ||||||||||
| Curing and finishing | 1day | ||||||||||
| Total construction period | 11days | ||||||||||
System bathroom (dry)
| Construction, (days) | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 |
|---|---|---|---|---|---|---|---|---|---|---|---|
| Delivery of product | 1day | ||||||||||
| Assembly and installing | 1day | ||||||||||
| Bath and sanitary equipment installation | 1day | ||||||||||
| Total construction period | 3days | ||||||||||